Update - The shop dry-fitted everything (left panel and centre stack) over the last few days. They completed the harnesses and connected everything, and then bench-checked the system. The Aspen, 530W, S-Tec 55 and SL-30 work seemlessly together with no glitches. Everyone is happy. Over the next day or two they will cut the new aluminum panels and dry-fit them to the panel frame to check for accuracy. Then they will send them off to be powder coated.

There are four 2" holes in the panel that will be plugged for the time being. Mid-Continent takes about 120 days to deliver the 2" ASI and Altimeter, and the other two 2" holes are for the cooling fans of the soon-to-be installed Aspens 1000 EFD and 500 EFD.